HLY-GEN-04: Pipe Storage Yard Grade Leveling, Safe Tier Stacking & OSHA Safety Protocol
العودة إلى قائمة الوثائق
عام
HLY-GEN-04: Pipe Storage Yard Grade Leveling, Safe Tier Stacking & OSHA Safety Protocol
October 4, 2026
HLY-GEN-04-Yard-Stacking-Safety-Manual.pdf
1. Storage Yard Concrete Paving & Drainage
Yard foundation must be compacted (compaction ratio $\ge$ 0.95) and paved with $\ge$
180 mm Grade C25 concrete slab
, rated for $\ge$ 150 kPa.
Slope yard surface 0.5%–1.0% toward drainage swales to prevent rainwater pooling and subbase softening.
2. Mandatory Safe Tier Stacking Limit Schedule
DN300 – DN600 Pipes
: Max allowable stack height is
4 to 5 tiers
;
DN800 – DN1200 Pipes
: Max allowable stack height is
3 tiers
;
DN1350 – DN1800 Heavy Pipes
: Max allowable stack height is
2 tiers
;
DN2000+ & Trenchless Jacking Pipes
:
Single-tier ground placement only. Stacking strictly prohibited!
3. Anti-Roll Chock Wedges & Stacking Dunnage Rules
Chock the bottom row on both flanks using 35° hardwood triangular wedges (min height 120 mm).
Alternate bell and spigot ends in successive tiers; place 50 mm thick timber runners between layers to prevent domino collapse accidents.
تنزيل المرفق
HLY-GEN-04-Yard-Stacking-Safety-Manual.pdf